What is the time limit for the Municipality to prepare a project or scheme in draft form, from the date of publication of the declaration of such project or scheme under Sub-Section (2) of Section 174 of the Rajasthan Municipalities Act, 2009?

Asked in RPSC Local Self Govt. Dept. (RO and EO) Re-Exam 2022

  1. Not later than three years
  2. Not later than two years
  3. Not later than one year
  4. Not later than four years
  5. Question not attempted
Show answer

Answer: C. Not later than one year