Which of the following statements is/are correct? 1. If 5 workers complete a task in 12 days, then 10 workers can complete the same task in 5 days. 2. If 8 workers complete a task in 14 days, then 4 workers can complete the same task in 30 days. Select the answer using the codes given below:

Asked in HPSC HCS (Ex. Br.) & Other Allied Services Paper II (CSAT) 2025

  1. 1 only
  2. 2 only
  3. Both 1 and 2
  4. Neither 1 nor 2
  5. Question not attempted
Show answer

Answer: D. Neither 1 nor 2