x, y and z can complete a piece of work in 9, 18 and 24 days respectively. They started working together, but y and z left the work 3 days and 2 days before the completion of the work respectively. What was the ratio of contribution of y to that of z in the completed piece of work ?

Asked in RPSC Prelims 2013

  1. 4:5
  2. 3:2
  3. 2:3
  4. 1:2
Show answer

Answer: A. 4:5

This previous-year question came without the commission's answer key; the answer was checked by AI. Always confirm with the official key.