10 One contractor had undertaken a construction work. To complete the given job, he sought labour comprising 24 men for 12 days for working 10 hours a day. But due to festival season, as the labour had gone to their respective hometowns, he could get only 15 men and they too were willing to work 8 hours a day. With this much labour, in how many days would he be able to complete the same job?

Asked in HPSC Prelims 2023

  1. 20 days
  2. 22 days
  3. 24 days
  4. 26 days
  5. (E) Question not attempted
Show answer

Answer: C. 24 days

This previous-year question came without the commission's answer key; the answer was checked by AI. Always confirm with the official key.