18 An underground panel in a coal mine is being developed by Bord and Pillar system. The pillar size is 35 m centre to centre and the adjacent galleries are 6 m wide. The percentage of extraction during development is :

Asked in HPSC to Final Answer Key of the Master Question Booklet of the Screening Test for the Posts of Mining Officer (Advt. No. 08/) & Assistant Mining Engineer (Advt No. 09/) 2023

  1. 24.9
  2. 26.2
  3. 31.3
  4. 44.6
  5. Question not attempted
Show answer

Answer: A. 24.9