25 In longwall caving method of coal mining, the thickness of immediate roof is calculated from:
Asked in HPSC to Final Answer Key of the Master Question Booklet of the Screening Test for the Posts of Mining Officer (Advt. No. 08/) & Assistant Mining Engineer (Advt No. 09/) 2023
Show answer
Answer: C. Seam thickness and bulking factor
More HPSC Prelims previous year questions questions
- 26 A longwall panel with a face height of 3.5 m and face length of 180 m is worked in 3 shifts per day employing 60 men per shift. The depth of the web of the shearer cutting coal is 0.6 m. The unit weight of the coal is 1.6 te/m3. Two full face cuts are executed per shift. The daily production from the panel in tonne is :
- 28 Which of the following does not fall under the category of Metallic minerals?
- 29 In an underground metal mine, 8 drift faces the blasted in a day. Drift dimensions are 3 m by 5 m and the average advance achieved per round is 2.4 m. If the designed powder factor is 1.8 m3/kg, the daily explosive requirement per day in kg is :
- 30 Choose the operations in their proper order for shaft sinking in solid rock.
- 31 Which of the following method of mining is applicable only to metal mining?
- 34 A mine has to drive in a vein deposit of strike length 2.8 km, width of 7 m with a road header. The average production capacity of the road header is 30 m3/hr with an average effective monthly cutting hour of 255. The planned largest plying machine requires an excavation height of 5 m. The time in months (rounded up to nearest whole number) required to complete the drive development work is :
- 35 Which of the following methods uses two different plastic tubes for installation of cable bolts?
- 36 Statements related to choice of location of a vertical shaft are given below. (1) Its location should be such that the transportation cost should be minimum. (2) There is competent rock mass. (3) Shaft location depends on size of a shaft pillar. (4) The shaft locations should not be hindered by the surface features.