35 Which of the following methods uses two different plastic tubes for installation of cable bolts?
Asked in HPSC to Final Answer Key of the Master Question Booklet of the Screening Test for the Posts of Mining Officer (Advt. No. 08/) & Assistant Mining Engineer (Advt No. 09/) 2023
Show answer
Answer: C. Retracted grout tube installation method
More HPSC Prelims previous year questions questions
- 36 Statements related to choice of location of a vertical shaft are given below. (1) Its location should be such that the transportation cost should be minimum. (2) There is competent rock mass. (3) Shaft location depends on size of a shaft pillar. (4) The shaft locations should not be hindered by the surface features.
- 37 High production rate coupled with large scale and extensive subsidence results from the method of
- 38 The equipment that is not used in hard rock metal mining drivage is
- 39 A void of 1800 m3 was formed during production of 5600 tons of copper ore in a stoping block. If the specific gravity of dry mill tailings used for backfilling the void is 2.6, then assuming dry conditions, what is the quantity of tailing (in tons) that would remain surplus after filling the same void:
- 40 Statements related to the context of permanent lining of shafts are given below- (1) Permanent lining is not required where the shaft sides are very strong and competent. (2) The shaft lining, in general, is constructed from top to bottom. (3) Only brick is used as permanent lining. (4) Shotcrete is also a type of permanent lining.
- 41 Statements on Shaft construction are - (1) Cementation sinking method is used for weak and watery rock medium. (2) Grab is a common loading equipment used in shaft sinking. (3) Freezing method is a very common method of shaft sinking. (4) Blasting cannot be adopted for sinking shaft due to accumulation of water.
- 42 The sales value of chromite ore from an open pit mine is Rs. 8000 per tonne. Cost of mining, excluding stripping cost, is Rs. 3500 per tonne. The cost of stripping is Rs. 1200 per m3. Assuming profit margin to be zero, the breakeven stripping ratio in m3/tonne is:
- 43 In an opencast coal mine, eight trucks are assigned for one shovel. The shovel loading time per truck is 6 min, and truck cycle time is 22 min. The match factor is: