39 A void of 1800 m3 was formed during production of 5600 tons of copper ore in a stoping block. If the specific gravity of dry mill tailings used for backfilling the void is 2.6, then assuming dry conditions, what is the quantity of tailing (in tons) that would remain surplus after filling the same void:

Asked in HPSC to Final Answer Key of the Master Question Booklet of the Screening Test for the Posts of Mining Officer (Advt. No. 08/) & Assistant Mining Engineer (Advt No. 09/) 2023

  1. 920
  2. 1020
  3. 4680
  4. 9620
  5. Question not attempted
Show answer

Answer: A. 920