42 The sales value of chromite ore from an open pit mine is Rs. 8000 per tonne. Cost of mining, excluding stripping cost, is Rs. 3500 per tonne. The cost of stripping is Rs. 1200 per m3. Assuming profit margin to be zero, the breakeven stripping ratio in m3/tonne is:

Asked in HPSC to Final Answer Key of the Master Question Booklet of the Screening Test for the Posts of Mining Officer (Advt. No. 08/) & Assistant Mining Engineer (Advt No. 09/) 2023

  1. 2.75
  2. 3.75
  3. 4.75
  4. 5.75
  5. Question not attempted
Show answer

Answer: A. 2.75