43 In an opencast coal mine, eight trucks are assigned for one shovel. The shovel loading time per truck is 6 min, and truck cycle time is 22 min. The match factor is:
Asked in HPSC to Final Answer Key of the Master Question Booklet of the Screening Test for the Posts of Mining Officer (Advt. No. 08/) & Assistant Mining Engineer (Advt No. 09/) 2023
Show answer
Answer: A. 1.1
More HPSC Prelims previous year questions questions
- 44 A 18 m3 dragline is deployed in an O.B. bench of an opencast mine. Assuming it works for 50 days at the rate of 5 hrs per shift an d 3 shifts per day with the cycle time, bucket fill factor, and operating efficiency of the dragline being 55s, 0.8 and 80% respectively. The total volume of O.B. in m3 handled by the dragline is:
- 45 A drive shaft of an engine develops torque of 600 N-m. It rotates at a constant speed of 49 rpm. The power transmitted by the shaft in kW is:
- 46 Which of the following is true with respect to Emulsion explosives:
- 47 For stowing in a mine, removal for the particles (de-sliming) from tailings is carried out to
- 48 Which of the following is used as a criterion for evaluation of blast vibrations in terms of its potential to cause damage to structures?
- 49 Statements with respect to cut-off grade are given below: (1) The minimum grade required for a mineral to be economically mined and extracted. (2) The maximum grade required for a mineral to be economically mined. (3) Material with grade above cut-off grade is considered as waste. (4) Cut-off grade does not influence the mineable reserve. Which of the following is true?
- 50 In PERT analysis, the expected time to complete an activity is computed from the three time estimates : a most likely time (m), an optimistic time (a), and pessimistic time (b) using the expression:
- 51 Activity durations in PERT and CPM are decided on the following considerations: