44 A 18 m3 dragline is deployed in an O.B. bench of an opencast mine. Assuming it works for 50 days at the rate of 5 hrs per shift an d 3 shifts per day with the cycle time, bucket fill factor, and operating efficiency of the dragline being 55s, 0.8 and 80% respectively. The total volume of O.B. in m3 handled by the dragline is:

Asked in HPSC to Final Answer Key of the Master Question Booklet of the Screening Test for the Posts of Mining Officer (Advt. No. 08/) & Assistant Mining Engineer (Advt No. 09/) 2023

  1. 565527
  2. 663227
  3. 764457
  4. 864457
  5. Question not attempted
Show answer

Answer: A. 565527