If an activity has a crash time of 4 days and a normal time of 6 days and the crash cost is Rs 2 Lakh, then what is the crash cost per day?
Asked in GPSC Gujarat Water Supply and Sewerage Board Engi. Service (Mechanical) 2025
Answer under review: our editors are checking this question. Try the other GPSC Prelims previous year questions questions meanwhile.
More GPSC Prelims previous year questions questions
- In PERT analysis, what is the standard deviation of the activity duration, given the Optimistic Time (OT), Pessimistic Time (PT), and most likely Time (TM)?
- What is the primary purpose of a Zener diode?
- Which of the following components is used for controlling the power factor in an AC circuit?
- What is the main function of a transformer in an AC circuit?
- What does the term “virtual ground” mean in an operational amplifier (op-amp) configuration?
- Bar ‘A’ has diameter d and length L. Bar ‘B’ has diameter 2d and length 2L. The ratio of extension of bar A to extension of bar B is
- A bar of uniform cross-section A and length L is suspended from top. The extension of the bar due to self-weight only in terms of Young’s modulus E and unit weight γ is
- The relationship among modulus of elasticity E, modulus of rigidity G and bulk modulus K is