In the context of PERT and CPM, what does the "slack time" or "float" of an activity represent?

Asked in GPSC Gujarat Water Supply and Sewerage Board Engi. Service (Mechanical) 2025

  1. The amount of time an activity can be delayed without affecting the project's overall completion time.
  2. The maximum time an activity can be delayed without increasing its cost.
  3. The total time required to complete the entire project.
  4. The time taken for all activities in a project to be completed simultaneously.