Which of the following statement(s) is/are true? (i) The duration along the critical path defines the shortest possible time required to complete a project (ii) The critical path is the longest sequence of dependent tasks in a project, and its total duration determines the project's minimum completion time

Asked in GPSC Engineering Aptitude 2024

  1. Only (i)
  2. Only (ii)
  3. Both (i) and (ii)
  4. Neither (i) nor (ii)
Show answer

Answer: C. Both (i) and (ii)

This previous-year question came without the commission's answer key; the answer was checked by AI. Always confirm with the official key.