A plant floor supervisor needs to decide which specific machine will process Job MCM402 on tomorrow morning and which operator will cover the early morning shift to meet an urgent client deadline. Which scheduling horizon and technique is the supervisor utilizing?

Asked in Kerala PSC General Manager (Project) Part-I -Kerala State Co-operative Coir Marketing Federation Ltd Question Paper Code: 176//OL Category Code: 103/2025 Exam: General Manager (Project) Part-I Date 2026

  1. Strategic enterprise scheduling
  2. Short-term scheduling
  3. Intermediate-range scheduling
  4. Long-range scheduling
Show answer

Answer: B. Short-term scheduling