A plant floor supervisor needs to decide which specific machine will process Job MCM402 on tomorrow morning and which operator will cover the early morning shift to meet an urgent client deadline. Which scheduling horizon and technique is the supervisor utilizing?
Asked in Kerala PSC General Manager (Project) Part-I -Kerala State Co-operative Coir Marketing Federation Ltd Question Paper Code: 176//OL Category Code: 103/2025 Exam: General Manager (Project) Part-I Date 2026
Show answer
Answer: B. Short-term scheduling
More Kerala PSC Prelims previous year questions questions
- A growing electronics manufacturer is evaluating whether it needs to lease an additional manufacturing plant, purchase more high-speed surface- mount technology machines, or hire a second shift of assembly workers to meet projected customer demand over the next three years. Which fundamental operations management activity is the company undertaking?
- Which international family of standards provides organizations with a framework to manage their environmental responsibilities, reduce their environmental footprint, improve resource efficiency, and comply with legal environmental regulations?
- Which organizational practice involves giving employees the autonomy, authority, and discretion to make decisions, solve problems, and take ownership of their work without constantly needing managerial approval?
- In a Materials Requirements Planning (MRP I) system, which document lists all the components, sub assemblies and raw materials, along with the quantities needed, to produce one unit of a finished product?
- In inventory management, the additional stock held as a buffer against unpredictable fluctuations in demand and supply is called:
- The phenomenon in supply chain management where small fluctuations in customer demand lead to increasingly larger variations in orders upstream is known as the:
- Under which inventory control system is a fixed quantity of stock ordered whenever the inventory level falls to a predetermined reorder point?
- In which supply chain arrangements does the supplier, rather than the customer, take responsibility for monitoring stock levels and deciding when and how much to replenish at the customer's location?
All 4,876 Kerala PSC Prelims previous year questions questions →