As per URDPFI guidelines, the sewerage collection system i.e., Sewer Network system, should be designed for the prospective population of ______, as its replacement is not possible during its use.
Asked in GPSC Town Planner, Class-1, (New Municipal Corporations)/ Junior Town Planner, Class-2, (New Municipal Corporations) 2026
Show answer
Answer: C. 30 years
More GPSC Prelims previous year questions questions
- Why are multiple generators used in the Smart Power Generation concept?
- Which authority has the power to identify and notify specific areas as 'Hilly Areas' for special developmental consideration?
- Consider the following statements regarding Hilly Area development: 1. The NBC definition considers both height from mean sea level and average slope. 2. Fragile ecosystems in these areas do not require conservation if developmental activities are notified. 3. Sound settlement planning is a requirement for these regions. Which of the statements given above are correct?
- Which of the following coastal features are notably found within the high-low tide line mark?
- In the context of environmental planning for mining activities, what is the required extent of the buffer zone measured from the periphery of the core zone for a Mining Lease (ML) area of 40 hectares?
- In demographic planning, what does the term "Cohort" specifically represent?
- As per URDPFI guidelines, regardless of the expected pedestrian traffic volume, the width of a footpath should not be less than
- Which essential parameter is used to determine the overall size and space requirements of an airport?