Balancing depth in irrigation canal section is
Asked in Mizoram PSC 12 Jr.Grade of MES (Civil) (Contract) under DM&RD 20151.General English2.General Studies3. Engineering Paper I4. Engineering Paper II5. Engineering Paper III
Show answer
Answer: B. Depth in which cutting and filling will be equal
This previous-year question came without the commission's answer key; the answer was checked by AI. Always confirm with the official key.
More MPSC Prelims previous year questions questions
- The process of distribution of water in irrigation is called
- The losses in canal are usually measured by a simple method known as
- Based on Silt theories for design of bed slope of irrigation canal
- Which of the following spillway types is having a profile of ‘S’ Shaped?
- The spillway suitable for situation where direct overflow is not permissible is
- A solid obstruction put across the river to raise its water level and direct the water into the canal is
- River training works in which the river is trained to provide sufficient depth for navigation during low stage of river is
- A process by which an alluvial river flowing allowing curves of bends abandons particular bank and establishing its main flow along a comparatively straight and shorter channel is