In CPM and PERT methods activities are connected with each other in ______ .
Asked in GPSC Provisional key (Prelim) - 40/2017-18 General Studies & Concerned Subject 2018
Show answer
Answer: A. finish-to-start manner
More GPSC Prelims previous year questions questions
- Precedence Network Analysis (PNA) method of network analysis better addresses the real life situation in a construction project than CPM because
- The volume of soil to be excavated in its in-place natural state is called
- One of the following is not a earth excavation and lifting equipment
- In construction project management, Sensitivity Analysis is a modeling technique used
- If a worker dies while working on a site, under which one of the following laws the compensation is payable?
- In case of a unit-price contract, if a contractor quotes higher rates for some items and lower for the other items in the tender, then such a tender is known as:
- In a civil engineering work contract, the purpose of appointing an arbitrator is to
- The main purpose of framing the conditions of contract is