Pessimistic time and optimistic time of completion of an activity are given as 10 days and 4 days respectively, the variance of the activity will be:
Asked in GPSC Provisional Key (Prelim) - 25/-23 Paper-2 2022
Answer under review: our editors are checking this question. Try the other GPSC Prelims previous year questions questions meanwhile.
More GPSC Prelims previous year questions questions
- In PERT the activity distribution is
- A minimal spanning tree in network flow models involves
- Customers arrive at a reception counter at an average interval rate of 10 minutes and the receptionist takes an average of 6 minutes for one customer. Determine the average queue length.
- The primary objective of crashing in CPM is
- The method used for solving an assignment problem is called
- If an opportunity cost value is used for an unused cell to test optimality, it should be
- If x is a decision variable of LPP and unrestricted in sign then this variable can be converted into x = x’ – x” so as to solve the LPP by simplex method, where:
- A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is