Ques # :55 For a long uncompensated line, the limit to the line loading is governed by:
Asked in RPSC 23Feb 2016Question Paper for VicePrincipal/Superintendent ITI Screening Test 2012(Electrical Engineering)VICE PRINCIPAL/SUPDT. ITI - 2012
Show answer
Answer: C. stability limit
More RPSC Prelims previous year questions questions
- Ques # :56 Two two-port networks are connected in cascade. The combination is to be represented as a single two-port network. The parameters of the network are obtained by multiplying the individual:
- Ques # :57 A generating station has a maximum demand of 50 MW, a load factor of 60 %, a plant capacity factor of 45 %. If the plant while running is fully loaded, the daily energy produced will be:
- Ques # :58 For transfer of maximum power in a single-phase line from one end to the other:
- Ques # :59 For a DC voltage, an inductor
- Ques # :60 If each branch of a Delta circuit has impedance \sqrt{3}Z then, each branch of the equivalent Star (Wye) circuit has impedance:
- Ques # :61 Load frequency controller is ..... ..... and excitation voltage controller is ..... .....
- As compared to cylindrical pole type rotors, salient pole type rotors are:
- Deflection of hot-wire instruments depends upon