Ques #: 68 What does CASE Tool mean:- 1) Tools used for analysis and design only 2) Any computer based tool for software planning , development and evolution 3) Any tool used for case study only 4) Tools for testing the software
Asked in RPSC 23Feb 2016Question Paper for VicePrincipal/Superintendent ITI Screening Test 2012(Computer Science)VICE PRINCIPAL/SUPDT. ITI - 2012
Show answer
Answer: B. Any computer based tool for software planning , development and evolution
More RPSC Prelims previous year questions questions
- Ques #: 69 Which of the following is an advantage of waterfall model ? 1) The model assume stage rigidity 2) Enforced disciplined approach 3) The model makes no allowance for prototyping 4) Relegating maintenance is limited to minor changes
- Ques #: 70 Which of the following is not a COCOMO-I MODEL ? 1) The early prototyping model 2) The early design model 3) The early testing model 4) The post-architectural model
- Ques #: 71 Waterfall model is not suitable for:- 1) Complex project 2) Small project 3) Accommodating project 4) None of these
- Ques #: 72 The following are the two main approaches to designing black box test cases :- 1) Equivalence class partitioning and Coincident object analysis 2) Equivalence class partitioning and Boundary value analysis 3) Boundary value analysis and Partitioning analysis 4) None of these
- Ques #: 73 Consider the following statements with respect to coding phase: I. Verification: It is the process of determining whether the output of one phase of software development conforms to that of its previous phase II. Validation: It is the process of determining whether a fully developed system conforms to its requirements specification. Which of the following is correct ? 1) I 2) II 3) Both are correct 4) None of the statements are correct
- Ques #: 74 Actual programming of software code is done during the ______ step in the SDLC. 1) Maintenance and Evaluation 2) Design 3) Analysis 4) Development and Documentation
- Ques #: 75 Identify the correct statement with respect to Evolutionary development:- 1) Evolutionary development usually has two flavors; exploratory development and throw-away prototyping 2) Very large projects are usually done using evolutionary development based approach' 3) It facilitates easy project management, through the high volume of documentation it generates 4) Sometimes the construction of a throw-away prototype is not followed by a re- implementation of the software system using a more
- Ques #:76 Determine the maximum sender window size for data transmission using 40 back N protocol with “N” is the maximum sequence Number:- 1) 2n – 1 2) N -1 3) N + 1 4) None of these