Ques # :88 Negative slack occurs when 1) Events stick to their schedule 2) There is deficiency of resources 3) Dummy activities are large in number 4) Activities lie on the critical path
Asked in RPSC 23Feb 2016Question Paper for VicePrincipal/Superintendent ITI Screening Test 2012(Mechanical Engineering)VICE PRINCIPAL/SUPDT. ITI - 2012
Show answer
Answer: B. There is deficiency of resources
More RPSC Prelims previous year questions questions
- Ques # :89 The depreciation in any particular year is charged as fixed percentage of the remaining value of asset. This approach is adopted in 1) Sinking fund 2) Diminishing balance 3) Annuity charge 4) Sum of year digits
- Ques # :90 In PERT the span of time between the optimistic and pessimistic time estimates of an activity is 1) 6σ 2) 3σ 3) 12σ 4) σ
- Ques # :92 The aim of value engineering is to
- Ques # :93 A company sells 14000 units of its products. It has a variable cost of Rs. 15 per unit. Fixed cost is Rs 47000 and total required profit is Rs 23000. Per unit product price ( in Rs ) will be :
- Ques # :94 Which one of the following is not the solution method of transportation method
- Ques # :95 In linear programming problem variables are
- Ques # :97 Which one of the following method can be used for forecasting the sales potential of a new product
- Ques # :98 If the demand of an item is doubled and the ordering cost is halved, the economic order quantity