Ques #:96 In the context of CPM/PERT, the term crashing of network implies 1) Project has gone out of control 2) Diverting resources from non-critical activities to critical activities for timely completion 3) Short circuiting non-critical events 4) Abandoning the project

Asked in RPSC 02Jun 2016Question Paper for Asst. Engineer (Mechanical) GWD Screening Test - 2014ASST. ENGINEER - 2014

  1. Project has gone out of control
  2. Diverting resources from non-critical activities to critical activities for timely completion
  3. Short circuiting non-critical events
  4. Abandoning the project