Using prismoidal method, what is the volume (m³) of earthwork, required for 6 m deep ditch, if the top and bottom dimensions are 4 m × 8 m and 8 m × 16 m respectively?
Asked in APPSC (Arunachal) Question Booklet (Set-A) of Paper I and Paper II 2026
Show answer
Answer: A. 448
More APPSC Prelims previous year questions questions
- What is the quantity (m³) of cement mortar required for plastering (both sides/faces) of wall with 10 m length and 10 m height with plastering thickness of 15 mm?
- Assertion (A): Inertia force always acts through the centroid of the body and is directed opposite to the acceleration of the centroid. Reason (R): It has always a tendency to retard the motion.
- What is the estimate (₹) for a room with a plinth area of 300 sq.m with rate of ₹3,500 per sq.m? (Consider the adds of 10% of electric installation and 6% of miscellaneous)
- Assertion (A): If the bending moment along the length of a beam is constant, then the beam cross-section will not experience any shear stress. Reason (R): The shear force acting on the beam will be zero everywhere along the length.
- Assertion (A): The change in bending moment between two cross-sections of a beam is equal to the area of the shearing force diagram between the two sections. Reason (R): The change in the shearing force between two cross-sections of beam due to distributed loading is equal to the area of the load intensity diagram between the two sections.
- If the shear force acting at every section of a beam is of the same magnitude and of the same direction, then it represents a
- The compaction factor of 0.95 between partially compacted (W_p) and fully compacted (W_f) concrete indicates what level of workability in the concrete?
- In a slump test, each layer of concrete is compacted by a steel rod 60 cm long and of 16 mm diameter for 20 times. This statement is