Which of the following represents the correct sequence in a typical purchasing cycle?
Asked in Kerala PSC General Manager (Project) Part-I -Kerala State Co-operative Coir Marketing Federation Ltd Question Paper Code: 176//OL Category Code: 103/2025 Exam: General Manager (Project) Part-I Date 2026
Show answer
Answer: B. Purchase requisition → Supplier Selection → Purchase Order → Receiving → Payment
More Kerala PSC Prelims previous year questions questions
- Which of the following is NOT normally considered a component of purchasing lead time?
- A company's actual demand for a product during a particular month is 12,000 units. The seasonal index for that month is 1.20. What is the deseasonalized demand?
- Which budget is prepared using the formula: Budgeted Sales + Desired Closing Inventory – Opening Inventory?
- When cumulative actual demand is consistently different from cumulative forecast demand, it indicates that the forecasting method may have:
- Which principle of purchasing emphasizes obtaining the required material in the right quality and quantity, at the right time and place, from the right source, at the right price?
- Which method of purchasing involves purchasing materials only for immediate requirements without maintaining buffer stock?
- The demand for a product during the last three months was 120, 150 and 180 units: Using a 3-month moving average, what is the forecast for the next month?
- A purchasing department finds that supplier manufacturing time has remained stable, while the total time between placing an order and making the materials available for use has increased. Which combination most plausibly account for the increase?