In a construction project using Earned Value Management (EVM) at a particular review date, the following data is available: • Planned Value (PV) = Rs. 40 lakh • Earned Value (EV) = Rs. 36 lakhs • Actual Cost (AC) = Rs. 48 lakhs Which of the following statements is correct?

Asked in GPSC Gujarat Engineering Service (Civil), Class-1 and Class-2 2026

  1. The project is ahead of schedule and underbudget
  2. The project is behind schedule and overbudget
  3. The project is behind schedule but underbudget
  4. The project is ahead of schedule but overbudget

Answer under review: our editors are checking this question. Try the other GPSC Prelims previous year questions questions meanwhile.