The optimistic, most likely and pessimistic time for an activity are 7 days, 15 days and 17 days respectively. The expected completion time (in days) of this activity is
Asked in GPSC Gujarat Engineering Service (Civil), Class-1 and Class-2 2026
Answer under review: our editors are checking this question. Try the other GPSC Prelims previous year questions questions meanwhile.
More GPSC Prelims previous year questions questions
- In the time-cost analysis, crash cost = 15000, normal cost = 10000, crash time = 5 and normal time = 10. Then the cost slope is ________
- In the Critical Path Method, a critical event is defined as
- A municipal corporation needs to accumulate Rs. 10 crores after 20 years for the replacement of a major bridge. They decide to deposit an equal amount at the end of each year into a sinking fund that earns 8% annual compound interest. The sinking fund factor (A/F, i, n) for i = 8% and n = 20 years is 0.02185. What is the annual deposit required (in Rs. crores)?
- Fulkerson’s rule is primarily used for numbering the
- A document containing detailed description of all the items of work along with their current rates is called
- In the detailed estimate, the areas are worked out to the nearest ________
- In the context of depreciation accounting for a road construction equipment, the term ‘scrap value’ is best defined as
- The plan of a building is in the form of a rectangle with center line dimensions of outer walls as 12.7 m × 15.7 m. If the thickness of the wall in superstructure is 0.30 m, then its plinth area (in m2) is