In a construction contract, which of the following is a characteristic of a Lump Sum contract?

Asked in GPSC Gujarat Engineering Service (Civil) Engineering Aptitude 2026

  1. The owner bears the highest risk of cost overruns due to unforeseen site conditions.
  2. The contractor has the strongest incentive to control costs and complete efficiently.
  3. It is most suitable when the scope of work is poorly defined or likely to change frequently.
  4. Payments are made based on actual quantities of work measured at site.
Show answer

Answer: B. The contractor has the strongest incentive to control costs and complete efficiently.

This previous-year question came without the commission's answer key; the answer was checked by AI. Always confirm with the official key.