During a construction project, a delay occurs due to an exceptionally heavy monsoon that is twice the 50-year return period rainfall. The contract has a force majeure clause. Which of the following is the most appropriate management action?

Asked in GPSC Gujarat Engineering Service (Civil) Engineering Aptitude 2026

  1. The contractor must bear the cost of delay and accelerate the project at his own expense.
  2. The owner can claim liquidated damages because the delay was foreseeable.
  3. The contractor is entitled to a time extension but not additional payment for idle resources, unless specified.
  4. Both time and cost are automatically compensated under standard FIDIC conditions without proof.
Show answer

Answer: C. The contractor is entitled to a time extension but not additional payment for idle resources, unless specified.

This previous-year question came without the commission's answer key; the answer was checked by AI. Always confirm with the official key.