A typical sequence of following development phases in a construction project is (P) Plan development, (Q) Commissioning (R) Concept analysis (S) Execution
Asked in GPSC Provisional key (Prelim) - 40/2017-18 General Studies & Concerned Subject 2018
Show answer
Answer: D. R-P-S-Q