The full form of PERT method of project network analysis is:

Asked in GPSC Provisional key (Prelim) - 40/2017-18 General Studies & Concerned Subject 2018

  1. Project Estimation and Review Technique
  2. Program Evaluation and Review Technique
  3. Project Estimation and Report Technique
  4. Partial Evaluation and Review Technique
Show answer

Answer: B. Program Evaluation and Review Technique