The base width of a rock fill dam, in comparison to that of an earthen dam is:
Asked in GPSC Deputy Soil Survey Officer, Class-II 2024
Show answer
Answer: B. Much smaller
More GPSC Prelims previous year questions questions
- The minimum size of gravel that will not move in the bed of the wide rectangular channel of depth 0.8 m and longitudinal slope 0.0042 is?
- What is the water application efficiency when, during a 10-hour irrigation session for a wheat crop, 400,000 liters were lost due to runoff and percolation, while 2,800,000 liters were delivered to the field?
- Which of the following sets is employed to manage seepage within the foundations of an earth dam?
- In case the concrete is to be transported by pumping, the slump should be
- In a Newmark’s influence chart for stress distribution, there are 10 concentric circles and 50 radial lines. The influence factor of the chart is?
- Drills used for drilling in soft rocks are
- The process of evaluating the rough cost of construction of a project is known as
- Which of the following statements accurately describes aspects of pressure distribution under a strip footing? (i) The pressure bulb under a strip footing develops longitudinally. (ii) The pressure bulb under a strip footing develops laterally. (iii) The contact pressure at the edges of a rigid footing on saturated clay is theoretically infinite.