Design of column strip and middle strip is carried out separately for
Asked in GPSC Provisional key (Prelim) - 40/2017-18 General Studies & Concerned Subject 2018
Show answer
Answer: C. Flat slab
More GPSC Prelims previous year questions questions
- For moderate exposure, the minimum nominal cover to reinforcement to meet durability requirements as specified by IS 456, 200 is
- A typical sequence of following development phases in a construction project is (P) Plan development, (Q) Commissioning (R) Concept analysis (S) Execution
- The full form of PERT method of project network analysis is:
- The full form of acronym CPM is:
- The CPM network analysis is a ______ based method useful for ______ .
- The PERT network analysis is a ______ based method useful for ______ .
- In CPM and PERT methods activities are connected with each other in ______ .
- Precedence Network Analysis (PNA) method of network analysis better addresses the real life situation in a construction project than CPM because