Ques # :98 For same load, unsupported length and end conditions a laced column as compared to a battened column :- 1) is stronger 2) is weaker 3) is equally strong 4) cannot be compared
Asked in RPSC 23Feb 2016Question Paper for VicePrincipal/Superintendent ITI Screening Test 2012(Civil Engineering)VICE PRINCIPAL/SUPDT. ITI - 2012
Show answer
Answer: A. is stronger
More RPSC Prelims previous year questions questions
- Ques # :99 Consider the following statements :- Bearing stiffeners are provided in a plate girder (a) to avoid local bending failure of flange (b) to prevent buckling of web (c) to strengthen the web (d) under uniformly distributed loads. Which of these statements are correct ? 1) (a) , (b) and (c) 2) (b) and (c) 3) (a) , (c) and (d) 4) (a) , (b) and (d)
- Ques # :100 The design wind speed depends upon (a) risk coefficient (b) topography of the area (c) size of the structure of the above, 1) (a) , (b) are correct 2) (b) , (c) are correct 3) (c) , (a) are correct 4) (a) , (b) and (c) are correct
- Ques #: 1 In casting process, which of the following cross section is preferred for runner? 1) Square 2) Rectangular 3) Trapezoidal 4) Circular
- Ques #: 2 Thickness of slush casting process is given by t = 0.577t^0.5 + 0.413. After pouring metal if we immediately invert the mould then what is the thickness of casting? 1) 0 2) 0.413 3) 0.99 4) 1.567
- Ques #: 4 Cycle time of resistance welding consists of 1) Squeeze time, weld time, hold time & on time 2) On time, weld time , hold time & off time 3) On time, weld time & off time 4) Squeeze time, weld time, hold time & off time
- Ques #: 5 Go gauge is made for ______ limit to inspect hole size . 1) Maximum material 2) Minimum material 3) Intermediate material 4) Optimum material
- Ques #: 6 Tool life equation for tools under consideration are as follows- HSS: VT^0.2 = 150, Carbide: VT^0.3 = 250, where V is cutting speed in m/min and T is the tool life in min. The breakeven cutting speed above which the carbide tool will be beneficial is:- 1) 54 m/min 2) 150 m/min 3) 194 m/min 4) 250 m/min
- Ques #: 7 When the ordering cost is increased to 4 times,the Economic Order Quantity(EOQ) will be increased to : 1) 2 times 2) 3 times 3) 8 times 4) Remains same